vendredi 18 février 2011

Assignment 3

1. Write a list of the major assumptions you have made in designing your project. Identify 3 key things you want to learn more about.

Some of the major assumptions I have made in designing my project are:
·         The local farmers and community members will build the gabions by themselves
·         The UNDP as well as the local partners (the water and forest and the agriculture department) will support the project.
·         The timeline of the project activities will be respected.
·         The budget estimated will be enough for the project implementation
·         The goal and objectives of the project will be achieved, (decreased inundation negative impacts, poverty alleviation, food security, decreased migration…)
I want to learn more about the following three key things:
·         Who will transfer to the community members the knowledge and skills on how to build the gabions.
·         How far the identified agencies are willing to financially support the project?
·         If respecting the timeline set by the project will help us meet our objectives?

2. Following the 8 steps in this module, develop an evaluation plan for your project. Use the headings below as a guide as well as the questions included throughout the module (see the  sections). You can also refer to the ‘Evaluation Plan Case Study’ in this module for help.

Project title: Building the resilience in a mountainous ecosystem and its people capacities to adapt to climate change

Project Manager: The local association president: Saïd Zirri

Purpose of evaluation: The evaluation aims at ensuring the follow up of each single activity of the project to make sure it was done in time and successfully. It’s also a tool to share the project progress with different stakeholders, especially with the donors. Also it’s a way to ensure timely adjustment in case something went wrong during the implementation.

Involvement of Stakeholders:  

·         As the project is considering holding some capacity building workshops, each workshop will be subject to an evaluation at the end of each realization. (Some evaluation sheets will be distributed to the participant to collect their impressions and satisfaction).


·         During the implementation of the project the partners’ representatives will be observing and assessing the success/quality of each single component in which they are involved.
         Indicators of achievement:
·         Number of forest and fruit trees planted,
·         Number of gabion built,
·         Number of volunteers engaged,
·         Number of participants in the capacity building workshops,
·         Operationalisation of the greenhouse.

Objective/s:        

Evidence required
How often/
When
Obtained from
Tree planted:
Forest trees
Fruit trees
Adaptable trees

3000
1000
400

Forest and water department.
Gabions built
3 per ravine
Agriculture department
Emergency action plan is developed
By the end of the workshop
Meteorological direction

Local food security
After January 2012
Local association


Evaluation tools and techniques to be used:
·         Evaluation sheets distributed to participants at the end of each activity/workshop,
·         Personal assessment done by the agencies’ staff,
Baseline information required:
·         The situation of the degradation of the ecosystem in the village,
·         The level of knowledge and skills that the community members have regarding adaptation to Climate Change,
·         The number of young people and the degree of poverty in the village.
Logistical & resource considerations:
Time – One year was estimated for the implementation of the project starting from November 2011, to respond to the different requirement for each activity.
Money – The contribution of the community is estimated as in kind donation (labor and food) the department of water and forest will contribute with forest plants, the meteorology direction will contribute with expertise. For the other component of the project, money needed is estimated to $US 5.464,10
People – The project relays greatly on the community people’s contribution as a major resource (Voluntarism).

Approach to the analysis of information: To analyze the information related to the project implementation, we need regular monitoring and timely execution of the tasks. A focus on the major challenges will be done to avoid delays and bad surprises.
         Reporting and communication of outcomes / learning:
Reporting is extremely important for two main reasons:
1.    It’s a way to share the progress of the project with the donors, highlighting the challenges and realizations)
2.    To communicate the lessons learned and the successes to the other stakeholders. Those lessons will be used for future project and initiatives.

mercredi 9 février 2011

Assignment 2

1.   As Project Manager how will you lead your team? How will you participate as a member of this team and simultaneously maintain your authority?
As a project Manager, I will:
  • Share my vision with my team,

  • Communicate Clearly,

  • Help the members to develop their skills,

  • Be able to develop a realistic work plan,

  • Monitor the progress of the project, and performance of the team members,

  • Be able to develop partnership with other actors, who share the same goals and objectives,
  • Respect each team member.

    Activity
    Period/Duration
    Expected Outcome
    Indicators of achievement
    Partners/Stakeholders involve
    Cost in US dollar 
    Responsible
    Objective 1:  By the end of the upcoming rain season we will plant 3000 forest trees on the mountain, with the assistance of the forest department.
    Digging the holes for the trees
    By the end of November 2011.
    Holes
    Number of holes
    Community members
    0
    Local association
    Trees transportation to the site
    At the beginning of the rain season.
    Trees transported
    Number of trees.
    Forest department.
    62
    Association
    Planting the trees.
    Just after the arrival.
    Trees planted
    Number of the trees
    Forest department.
    611
    Forest department
    Objective 2:  By the end of March 2012, the community farmers will plant 1000 fruit trees on the hill (almond, olives, apples, cherries…) as identified with the agriculture department.
    Digging the holes for the trees
    By the end of February 2012
    Holes
    Number of the holes
    Community members
    0
    Association
    Purchase and transportation of the fruit trees.
    At the beginning of March 2012
    Trees transported
    Number of the trees
    Community members
    2$ per tree
    Association
    Planting
    Just after the reception of the trees
    Trees planted
    Number of the trees
    Community members
    0
    Association
    Objective 3: On June 2012, the community members will build 3 gabions along each ravine
    Purchase and transportation of the materials and equipments.
    At the beginning of June
    Gabions build
    Material and Equipment in site
    Agriculture Department
    3051
    Agriculture Department /Association
    Construction of the gabions
    June
    Gabion build
    Number of build gabion
    Agriculture Department – UNDP- Forest Department

    Local association members
    Objective 4: During the upcoming rain season, the community members will plant specific tree (400 trees) around each gabion.
    Digging the holes for the trees
    Beginning of December
    Holes
    Number of holes
    Community members
    0
    Local association
    Transportation of the trees
    End of December
    Trees transported
    Number of trees.
    Forest department.
    61
    Association
    Planting those trees
    End of December
    Trees planted
    Number of the trees
    Forest department.
    245
    Forest department
    Objective 5: By the end of the year, the community leaders will consolidate the irrigation system through underground canalization.
    Purchase/Transportation of the piping and other materials
    Sept- Dec
    Equipment on site
    New ditch build
    Agriculture Department – UNDP- Forest Department

    Association
    Construction of the new ditch
    Dec
    New ditch build
    New ditch build
    Agriculture Department – UNDP- Forest Department

    Association
    Objective 6: 20 farmers will benefit from 2 workshops on best practices and best crops to adapt to Climate Change. (March – April)
    Identify  a venue for the workshops
    Feb- March


    Association
    0
    Association
    Send invitations
    Feb -March


    Association
    13
    Association
    Identify facilitators
    Feb -March


    Agriculture Department/Association
    0
    Agriculture Department/Association
    Hold the workshops
    March - April
    A list of best practices and best crops
    Workshops held and number of participants
    Agriculture Department/Association
    184x2
    Agriculture Department
    Objective 6:  50 community members, including local authorities will benefit from 2 workshops on early warning and preparedness to intense rain (July – August)
    Identify  a venue for the workshops
    June - July


    Association
    0
    Association
    Send invitations
    June - July


    Association
    13
    Association
    Identify facilitators
    June - July


    Meteorological department/Association
    0
    Meteorological department/Association
    Hold the workshops
    July – August
    An Emergency action plan
    Workshops held and number of participants
    Meteorological department/Association
    184x2
    Meteorological department/Association
    Objective 7: 15 community members will benefit of workshop on how to build gabions (June – July)
    Identify a pilot site
    May- June


    Association
    0
    Association
    Send invitations
    May- June


    Association
    13
    Association
    Identify a facilitator
    May- June


    Agriculture Department/Association
    0
    Agriculture Department/Association
    Hold the workshop
    June- July
    A local knowledge and expertise to build Gabions
    Workshops held and number of participants
    Agriculture Department/Association
    184x2
    Agriculture Department
    Objective 8: The community members will install a greenhouse to raise the local community vegetables and needs; to insure the local food security. (January – February)
    Purchase and installation
    January


    UNDP – Association- Agriculture Department
    488
    Association
    Identify the management team
    January


    UNDP – Association- Agriculture Department
    0
    Association
    Preparation of the greenhouse for the effective exploitation
    February
    An installed and ready to operate  greenhouse
    An installed and ready to operate  greenhouse
    Management team
    0
    Association

3.   Who will be responsible for the management of finances (money) for the project?  What are the basic principles you have adopted for managing the funds for the project? (Bank account, signatories, petty cash float, receipting, cashbook and ledger entries, etc.)

The local association will create a Bank account for the project.

2.   Draw up a timeline for your project.  Include the major tasks people will carry out and identify the ‘milestones’ that mark the completion of key activities.  Don’t forget to plan the training sessions you expect staff and volunteers to take part in, and who will conduct these training sessions.

4.   Does your organization have in place some basic principles for managing people?  If yes, how will you make sure that volunteers are aware of the principles that affect them?  If not, what do you believe are the basic principles for managing people?  What steps will you take to monitor the effectiveness of specific project team members?   How will you ensure that there are rewards, especially for volunteers in the project team?  And how will you know that they have been effective?
So far, we don’t have any material to manage our volunteers. However, besides some training that are foreseen to develop the team spirit and the staff, we are thinking of designing a manual for them. This manual will give them an insight about their job description (what to do and how to do it the best way).
7.   Create a budget for your entire project/venture/enterprise cost, highlight all the costs for the project, but certain elements of your project might not need a budget but human resource etc
Project activity
Unit/Quantity
Unit coast in US dollar 
Total in US Dollar
Planting forest trees
3000
0
0
Planting fruit trees
1000
2
2000-
Building gabions
3 per ravine
305
915
Consolidating the irrigation system

1300
1300
Workshops on best practices and best crops to adapt to Climate Change.
2
184
368
Workshops on early warning and preparedness to intense rain
2
184
368
workshop on how to build gabions
1
85.5
85.5
Installing a greenhouse
1
427.6
427.6
Grand Total

 
5464.1