Assignment 2

1.   As Project Manager how will you lead your team? How will you participate as a member of this team and simultaneously maintain your authority?
As a project Manager, I will:
  • Share my vision with my team,

  • Communicate Clearly,

  • Help the members to develop their skills,

  • Be able to develop a realistic work plan,

  • Monitor the progress of the project, and performance of the team members,

  • Be able to develop partnership with other actors, who share the same goals and objectives,
  • Respect each team member.

    Activity
    Period/Duration
    Expected Outcome
    Indicators of achievement
    Partners/Stakeholders involve
    Cost in US dollar 
    Responsible
    Objective 1:  By the end of the upcoming rain season we will plant 3000 forest trees on the mountain, with the assistance of the forest department.
    Digging the holes for the trees
    By the end of November 2011.
    Holes
    Number of holes
    Community members
    0
    Local association
    Trees transportation to the site
    At the beginning of the rain season.
    Trees transported
    Number of trees.
    Forest department.
    62
    Association
    Planting the trees.
    Just after the arrival.
    Trees planted
    Number of the trees
    Forest department.
    611
    Forest department
    Objective 2:  By the end of March 2012, the community farmers will plant 1000 fruit trees on the hill (almond, olives, apples, cherries…) as identified with the agriculture department.
    Digging the holes for the trees
    By the end of February 2012
    Holes
    Number of the holes
    Community members
    0
    Association
    Purchase and transportation of the fruit trees.
    At the beginning of March 2012
    Trees transported
    Number of the trees
    Community members
    2$ per tree
    Association
    Planting
    Just after the reception of the trees
    Trees planted
    Number of the trees
    Community members
    0
    Association
    Objective 3: On June 2012, the community members will build 3 gabions along each ravine
    Purchase and transportation of the materials and equipments.
    At the beginning of June
    Gabions build
    Material and Equipment in site
    Agriculture Department
    3051
    Agriculture Department /Association
    Construction of the gabions
    June
    Gabion build
    Number of build gabion
    Agriculture Department – UNDP- Forest Department

    Local association members
    Objective 4: During the upcoming rain season, the community members will plant specific tree (400 trees) around each gabion.
    Digging the holes for the trees
    Beginning of December
    Holes
    Number of holes
    Community members
    0
    Local association
    Transportation of the trees
    End of December
    Trees transported
    Number of trees.
    Forest department.
    61
    Association
    Planting those trees
    End of December
    Trees planted
    Number of the trees
    Forest department.
    245
    Forest department
    Objective 5: By the end of the year, the community leaders will consolidate the irrigation system through underground canalization.
    Purchase/Transportation of the piping and other materials
    Sept- Dec
    Equipment on site
    New ditch build
    Agriculture Department – UNDP- Forest Department

    Association
    Construction of the new ditch
    Dec
    New ditch build
    New ditch build
    Agriculture Department – UNDP- Forest Department

    Association
    Objective 6: 20 farmers will benefit from 2 workshops on best practices and best crops to adapt to Climate Change. (March – April)
    Identify  a venue for the workshops
    Feb- March


    Association
    0
    Association
    Send invitations
    Feb -March


    Association
    13
    Association
    Identify facilitators
    Feb -March


    Agriculture Department/Association
    0
    Agriculture Department/Association
    Hold the workshops
    March - April
    A list of best practices and best crops
    Workshops held and number of participants
    Agriculture Department/Association
    184x2
    Agriculture Department
    Objective 6:  50 community members, including local authorities will benefit from 2 workshops on early warning and preparedness to intense rain (July – August)
    Identify  a venue for the workshops
    June - July


    Association
    0
    Association
    Send invitations
    June - July


    Association
    13
    Association
    Identify facilitators
    June - July


    Meteorological department/Association
    0
    Meteorological department/Association
    Hold the workshops
    July – August
    An Emergency action plan
    Workshops held and number of participants
    Meteorological department/Association
    184x2
    Meteorological department/Association
    Objective 7: 15 community members will benefit of workshop on how to build gabions (June – July)
    Identify a pilot site
    May- June


    Association
    0
    Association
    Send invitations
    May- June


    Association
    13
    Association
    Identify a facilitator
    May- June


    Agriculture Department/Association
    0
    Agriculture Department/Association
    Hold the workshop
    June- July
    A local knowledge and expertise to build Gabions
    Workshops held and number of participants
    Agriculture Department/Association
    184x2
    Agriculture Department
    Objective 8: The community members will install a greenhouse to raise the local community vegetables and needs; to insure the local food security. (January – February)
    Purchase and installation
    January


    UNDP – Association- Agriculture Department
    488
    Association
    Identify the management team
    January


    UNDP – Association- Agriculture Department
    0
    Association
    Preparation of the greenhouse for the effective exploitation
    February
    An installed and ready to operate  greenhouse
    An installed and ready to operate  greenhouse
    Management team
    0
    Association

3.   Who will be responsible for the management of finances (money) for the project?  What are the basic principles you have adopted for managing the funds for the project? (Bank account, signatories, petty cash float, receipting, cashbook and ledger entries, etc.)

The local association will create a Bank account for the project.

2.   Draw up a timeline for your project.  Include the major tasks people will carry out and identify the ‘milestones’ that mark the completion of key activities.  Don’t forget to plan the training sessions you expect staff and volunteers to take part in, and who will conduct these training sessions.

4.   Does your organization have in place some basic principles for managing people?  If yes, how will you make sure that volunteers are aware of the principles that affect them?  If not, what do you believe are the basic principles for managing people?  What steps will you take to monitor the effectiveness of specific project team members?   How will you ensure that there are rewards, especially for volunteers in the project team?  And how will you know that they have been effective?
So far, we don’t have any material to manage our volunteers. However, besides some training that are foreseen to develop the team spirit and the staff, we are thinking of designing a manual for them. This manual will give them an insight about their job description (what to do and how to do it the best way).
7.   Create a budget for your entire project/venture/enterprise cost, highlight all the costs for the project, but certain elements of your project might not need a budget but human resource etc
Project activity
Unit/Quantity
Unit coast in US dollar 
Total in US Dollar
Planting forest trees
3000
0
0
Planting fruit trees
1000
2
2000-
Building gabions
3 per ravine
305
915
Consolidating the irrigation system

1300
1300
Workshops on best practices and best crops to adapt to Climate Change.
2
184
368
Workshops on early warning and preparedness to intense rain
2
184
368
workshop on how to build gabions
1
85.5
85.5
Installing a greenhouse
1
427.6
427.6
Grand Total

 
5464.1